HYPERTECH ENGINEERING
|
Steps for Treatment : |
(1) |
Flooring Protection using POP |
(2) |
Removing Existing Plaster from Wall |
(3) |
Drilling holes into Wall Thickness |
(4) |
Fixing of PVC Tubes & Brick joints by Integral Waterproofing Chemical |
(5) |
Pouring Two Chemicals into holes for absorption & make Gel type Barrier |
(6) |
Next day Sealing holes by Cement Slurry & Expansive Additives |
(7) |
Apply negative water pressure & crystallization penetration chemical |
(8) |
New Double coat plaster with Integral Waterproofing Chemical |
(9) |
Cleaning & Removal of Debris |